This topic describes the steps to run a task to verify whether or not the Quest On Demand - Migration - Power Apps enterprise application service principal is granted the necessary permissions to work with the Power Apps application in the source and target tenants.

Starting the Test Power Apps Connection Task

  1. Log in to Quest On Demand and choose an organization if you have multiple organizations.
  2. From the navigation pane, click Migrate > Projects to open the My Projects list.
  3. Create a new project or open an existing project.
  4. Click the Power Apps tile, or click Open from the Power Apps tile to open the Power Apps migration workspace.
  5. Open the Dashboard tab. Then click Connect to Power Apps to start the Connect to Power Apps wizard. Each step is described below:
  6. Prerequisite Setup

    This is an information step that tells you to verify that you have manually completed the setup steps described in the Granting Additional Permissions topic. If you have not competed the manual setup steps, you must do it now.

  7. Schedule
    1. Choose from one of three options to schedule the task. The scheduler will be activated only after you complete the task wizard.
      • Run now - task runs immediately.
      • Run later - task must be started manually.
      • Schedule - task will be started at a future date and time entered in the corresponding calendar field.
    2. Click Next.
  8. Summary
    1. Verify the task specifications as described below:
      1. Name - name of the task. You can specify a custom name. Default name is Test Power Apps Connection.
      2. Scheduled start - date and time when the task will start. Now indicates that the task will start immediately.
    2. Click Back to revise or review a previous step or click Finish to complete the task wizard and start the task as scheduled.

You can track its progress in the Tasks tab, view the summary on the Dashboard or monitor alerts and notifications in the Events tab.

Reviewing the Test Power Apps Connection Task

  1. Open the Tasks tab.
  2. Select the Power Apps task that you want to review.
  3. In the task details pane that opens, the information presented is as described below:
    1. Task Status - Status of the task.
    2. Type - Type of the task. The type is TestPowerAppsConnection.
    3. Created - Date and time when the task was created.
    4. Modified - Date and time when the task was last updated.
    5. Last Operation - The action that was most recently performed in this task.
    6. Schedule - Date and time when the task started. Now indicates that the task started immediately after the task was created.
    7. Events (number) - Number indicates the count of events that the task encountered. The values indicate the type of the events and the event count for each type.

Reviewing the Test Power Apps Connection Task Events

  1. Open the Tasks tab.
  2. Select the Test Power Apps Connection task for which you want to review the events.
  3. In the task details pane that opens, click Events (number). The Events tab opens with a filtered list of events for the selected task.
  4. Select an event that you want to review. In the task details pane that opens, the information presented is as described below:
    1. Object - name of the Power Apps object if applicable.
    2. Task - name of the task.
    3. Time - date and time when the event occurred.