Stat 7.0 - Web User Guide

Stat Web
Stat Web Queries CSRs Workflow Tasks CSR Logs CSR History CSR Migration Path Job Monitor Test Connect Reports
About us Index

Posting time to tasks

Stat® allows you to track the progress of a task by entering the exact time spent on it. Post the time in the Task Entry section of the Tasks window.
NOTE: Although you cannot post time to tasks opened directly from read-only CSRs, with proper security rights, you can post time to any task opened from a Task Query list, including tasks not assigned to you and tasks associated with closed or read-only CSRs.
From a CSR: Click the Tasks link in the View tab of the CSR window, and select the task.
From a Task Query: In a Task Query list, select the task.
2
Scroll down to the Time Entries section, which displays tasks already saved to the Stat Repository.
5
Click in the User field and select the user that performed the work.
6
In the Hours fields, enter the number of hours spent on the task. You can use decimals to post portions of an hour, for example, 4.35.
8
When finished, click Add to save the time entry.
Stat automatically updates the Actual Hours field with the total number of hours posted as time entries. If you want to delete a time entry, select the row from the list of time entries and click Delete.

6

CSR Logs

Viewing CSR log files

The Log window displays all the logs that have been added to the CSR, either by the user or automatically by Stat® when it sends or receives an email associated with the CSR, or when the CSR lock is overridden.
Click Logs section.
1
Click New Log.
2
In the Topic field, assigned a topic to the log topic.
3
Optionally, select the Confidential option.
4
In the Details field, enter the contents of the log.
5
Click Create.

7

CSR History

相关文档
Showing 1 to 6 of 6 rows

The document was helpful.

选择评级

I easily found the information I needed.

选择评级