(Only for Oracle 10g release or later)
Assign resource plans to activate at different times such as during specific peak or off-peak periods.
Button | Description |
---|---|
New |
Click to create a window
Click Save. The new window will appear in the Windows list above. Click Enabled to activate the window. |
Save | Save changes to a selected window or a new window. |
Advanced | Edit available Attribute Values for the selected item. |
Open | Activate the selected Window and commence running the scheduled jobs based on the durations currently entered. You can change the duration values if required. |
Close | Stop the currently active window. Any jobs using that window as their schedule which were started at the beginning of this window and have indicated that they must be stopped on closing of the window will be stopped. |
Drop | Remove the selected item from the database. |