Copying ACL information


Previous

During a migration, you can choose to update access control lists (ACLs) with new security identifiers (SIDs) for the objects being migrated and to remove their SID history.

To update ACLs with new SIDs

1    Click Jobs, and expand the job.

2    Click Other File Options.

3    Select the options to update ACLs.

Table 16. ACL update options

Option

Description

Update ACLS which use SID history

Select to update ACLs that use SID history, and type a Lightweight Directory Access Protocol (LDAP) domain path.

During a migration, the SIDs of the objects being migrated are checked against the SID History specified in the LDAP domain path box. If the SIDs of the objects being migrated are on the list, the ACLs are updated with new SIDs for the migrated objects and their SID history is cleared.

Copy SACL

Select to copy security information.

Remove Orphaned SIDs

Select to remove orphaned SIDS.

Map SIDs Using Quest Migration Manager for AD map file

If you created a map file using Quest™ Migration Manager, select the check box, and click Browse to locate the map file.

·         To view the contents of the map file, click View.

·         By default, source permissions on the target are retained. If you do not want to retain the permissions, clear the Leave source accounts permissions on target check box.

·         If you want to copy only permissions for accounts that are included in the Migration Manager INI map file and ignore all other permissions from the source, select Translate only accounts found in the map file.

NOTE: If you select Translate only accounts found in the map file, the Leave source accounts permissions on target check box is cleared and vice versa. Both checkboxes cannot be selected at the same time.

Next


Running pre and post migration tasks


Previous

You can choose to run a task either before or after a migration.

1    In the Jobs pane, expand the job.

2    Click Other File Options.

3    Choose to run a task either before or after the migration.

Table 17. Pre and post migration options

Option

Description

Run a Pre-Migration Task

Select to run a task before the migration begins. Click Browse to locate an executable (*.exe or *.cmd) or type the path into the box.

Run a Post-Migration Task

Select to run a task after the migration completes. Click Browse to locate an executable (*.exe or *.cmd) or type the path into the box.

If a fatal error occurs, cancel all tasks including the migration.

Select to cancel all pending tasks and the migration if a fatal error occurs during the execution of a task or the migration.

Next


Sending email notifications


Previous

You can send an email notification when either a job has completed or has not completed by a specified date and time.

To set up email notifications

1    Click Jobs, and expand the job.

2    Click Email.

3    Select Send email notification.

4    Select the condition on which the email notification is sent.

Table 18. Email notification options

Option

Description

When job completes

Select to send an email to the specified recipients when the copy job completes successfully.

If job has not completed by

Select to send an email to the specified recipients only if the copy job has not completed by the date and time specified. To change the date and time, click an item in the box, and then use the arrow keys to change the value.

If job is not completed within hh:mm:ss

Select to send an email to the specified recipients only if the copy job has not completed within the time period specified. To change the time period, click an item in the box, and then use the arrow keys to change the value.

If job fails

Select to send an email to the specified recipients if the job fails.

5    To add recipients, click Add, type the name of the recipient, and click OK. Repeat for each recipient.

6    Type the text to appear in the subject line of the email.

To change the email settings for the copy job

    Click Email Settings. See Setting SMTP settings.

NOTE: The SMTP settings override those set using Tools | New Job Options | SMTP Settings.

To send reports with the email

1    Select Attach job reports.

2    Click Select Reports.

3    Select the reports to attach to the email.

4    Click OK. The number of reports you select displays on the Email tab.

By default, if the reports exceed 50 MB, the reports are not attached. To stop the attachment of the selected reports if the total size exceeds the value in the box, select Do not attach reports if their total size exceeds x MB, and enter a value.

                                                          3

Next


Running copy jobs


Previous

    Starting a copy job

    Restarting a copy job

    Importing a job

    Restoring job settings

    Scheduling jobs

    Managing scheduled jobs

    Viewing job status

    Viewing logs and reports

    Viewing copy job statistics

    Viewing log file contents

    Exporting logs

    Deleting logs

    Running reports

    Analyzing file systems statistics

Next


Verwandte Dokumente

The document was helpful.

Bewertung auswählen

I easily found the information I needed.

Bewertung auswählen