Exchange Processing Wizard (EPW) running for more than period of times and stuck at certain percentage.
If right click and "Start" , the message shows "The exchange processing is already running".
WORKAROUND:
Important: before doing any changes to ADAM/ADLDS database, please make sure that it was backed up!
To successfully restart the process, do the following:
If there's no CN=Lock container found, then the whole CN={GUID} of the stuck task and its subcontainers must be deleted. Attempt to write down task's parameter if they're still accessible prior to deletion.
Once, CN={GUID} was deleted, start QMM console and recreate the same task again.
Note: In some cases, you may not find CN=Lock. If after rebooting the server the task remains the same, it may be "stuck" in the ADAM database.
Look for the task specified in step 6 above and find the task's status; change it from 3 to 1. This will allow the task to be recognized as "not running" and be modifiable.