Level 0 or Full Backup: A Full Backup provides a backup of all the data in the selected path. |
• |
Level 1 through 9 or Incremental Backup: The Incremental Backups base themselves on the most recent lower‑level Incremental Backup, and include any data that has changed or is new since the last Full or Incremental Backup. |
1 |
In the Navigation pane, click Create Backup Job. |
2 |
In Job Name, specify a name for the job. |
3 |
In the Selections list, select an existing Backup Selection Set, or complete the following steps to create a set. |
a |
b |
• |
Back up all volumes: Select the Volumes node. |
• |
Back up individual volumes: Open the Volumes node, and select the volumes that you want to back up. |
e |
Click Save, and in the Create New Set dialog box, type a name for the set. Click Save to close the dialog box. |
NOTE: A set name can contain alphanumeric and non-alphanumeric characters, but it cannot contain non‑Latin characters. On Linux® OS, the names can have a maximum of 200 characters. On Windows® OS, there is no length restriction. However, a maximum of 40 characters is recommended on all platforms. |
4 |
In the Plugin Options list, select an existing Backup Options Set, or complete the following steps to create a set. |
a |
b |
Under NDMP Backup Options, configure the following settings. |
The file “/etc/dumpdates” keeps a record of the backup, including the backup name, backup level, and snapshot time.
| |
c |
Under Sub Jobs, configure the following settings. |
By default, each subjob is listed on the Job Status page. This can create confusion when you try to view the details of the parent job. To include only a single entry for the parent job, leave this check box selected. |
d |
Click Save, and in the Create New Set dialog box, type a name for the set. Click Save to close the dialog box. |
5 |
Select or create the Schedule Set, Target Set, and Advanced Options Set. For more information about these sets, see the Dell NetVault Backup Administrator’s Guide. |
6 |
To submit the job for scheduling, click Save & Submit. You can monitor the job progress from the Job Status page and view the logs from the View Logs page. |
1 |
In the Navigation pane, click Create Backup Job. |
2 |
In Job Name, specify a name for the job. |
3 |
4 |
5 |
6 |
In the NDMP Backup Request dialog box, configure the following option: |
• |
Directory: Specify the full path to the directory that you want to back up. Use the following format to specify the backup path: |
7 |
Set the Dump Level and the remaining backup options. |
8 |
Click OK to save the settings. |