Using Foglight Hybrid Cloud Manager for AWS Monitoring Tab System Info Tab Tags Tab Report Tab Rule Configuration Tab Administration Tab Optimizer Tab Cost Tab Policy Management Tab

Schedule view

The Schedule view enables users to create, edit, delete, or copy a schedule.

Figure 31. Schedule view

Click Add and a Create Schedule dialog box appears.
1
Occurrence: Select the start date and start time and click Next.
2
Recurrence: Select the recurrence and click Next.
a
Specify the Recurrence Pattern according to the screen prompt. Click Next. For detailed information of the Recurrence Pattern, see Recurrence Pattern .
b
Choose Never Stop or specify an End Time. Click Next.
3
Summary: Specify a name for the schedule and descriptions for the schedule. Click Finish.
Click Copy and a Copy [Schedule name] dialog box appears. Edit the schedule name and description. Click OK.

The schedule list refreshes and the newly-created schedule will be displayed in the list.

2
A Delete Schedules Confirmation dialog box appears.
3
1
Click the schedule you want to edit and an Edit Schedule dialog box appears.
2
Click the schedule and an Edit Schedule Item dialog box appears.
3
Edit the Occurrence, Recurrence, and Summary if necessary and click Finish.

Recurrence Pattern

Once

Starts at a specified date and time, for a specified duration, and ends at a defined end date and time.

N/A

Interval

Starts at a specified time and date for a certain duration, repeats at specified time periods, with or without a defined end date and time.

Specify Every xx and select from Days, Hours, Minutes, or Seconds.

Daily

Starts at a specified time and date, runs for a whole day or a fraction of a day, repeats at a regular interval of days, with or without a defined end date and time.

Specify Every xx days.

Weekly

Starts at a specified time and date, runs for a whole day or a fraction of a day, repeats at a regular interval of weeks on one or more days of the week, with or without a defined end date and time.

Specify Every xx week (s) and select the weekdays.

Monthly

Starts at a specified time and date, runs for a whole day or a fraction of a day, repeats at a regular interval of months on one or more days of the month, with or without a defined end date and time.

Select by Day or Week.

Specify Day xx of Every xx month(s).

Yearly

Starts at a specified time and date, runs for a whole day or a fraction of a day, repeats at a regular interval of years on one or more days of the year, with or without a defined end date and time.

Select by Day of Month or Week of Month.

Specify the date and select the month.

 

Policy Executed History view

The Policy Executed History view shows the detailed history records of the executed policy by each Resource.

Run Reports for Policy Management

Click Reports on the top right corner of the interface and choose All Polices Execution Report. An All Polices Execution Report dialog box will appear. Fill in required information to run the report.

The All Polices Execution Report will summarize the status for all of the Policies Execution.

 