The coodinator is running slow. Change Auditor Client takes a while to open.
To narrow down the events that need to be tuned check the following:
In the system tray on the ChangeAuditor Coordinator, go to Change Auditor coordinator system tray,
Right click | coordinator status.
If the coodinator status is not "running", go to coordinator system tray, right click | enable coordinator.
Go back to the coordinator status, and once this goes to a running state.
Note the number of events in the receive buffer.
Next step is to open changeAuditor client on the server,
select View | searches
On the left pane, navigate to and select "All Events".
In the right hand pane, scroll to the "All Events" search, right click | Run
In the All events tab that shows, drag the column "Event" to the section above that says "Drag a column header here to group by that column".
Click the button for pie chart. This is the middle button to the right of where the "event" column was dragged to.
Take note of the event that is occurring most in the chart.
You can then drag "event" back to the main pane.
Repeat this for the column "User" and take a screen shot of the pie chart.
Also taking note of the user account that produces the most events.