Scheduled Reports not running consistently.. Scheduled report some times run fine and then they stop working and strat working again after no know change. The reports seem to stop and start working at random.
Reviewing the coordinator logs you may see:
[ERROR][ChangeAuditor.Coordinator.ReportProcessorTask._RunReport(0)] Low Memory Aborting! 16384 Total, 1638.258 Available 10%
Possible causes are:
Reports that are returning large amounts of data (results) consume coordinator memory. Ensure that the minimum specifications for all Coordinators in the environment are met. *Note: Depending on the environment additional resources may be required beyond minimum specifications.
If there are multiple Coordinators in the environment, ensure that all Coordinators can communicate with the SMTP server. If one Coordinator is a firewalled network (where the SMTP port, 25, is blocked) this can prevent reports from being emailed from this Coordinator.