立即与支持人员聊天
与支持团队交流

Replicator 7.4 - Evaluation Guide

Replicating Workflows

This scenario demonstrates the capability of Replicator to replicate in-process workflows. You must first ensure that capturing workflows is selected on your Map Family configuration settings. You will then add a workflow, start it on an item, and complete the workflow.

1.Go the Manage Map Families in Central Administration for both your source and target web applications. Select the Map family, and click View Maps.
METALO~1_img14

2.Select the Map Family, this will take you to the Configure Replication Map Settings page. Here, select All Events for workflows.
METALO~1_img15

3.Click Ok.

4.In a web browser, open your source web application.

5.Add an Approval workflow to a list or library.
METALO~1_img16

6.Start the approval workflow on an item in the list or library.
METALO~1_img17

7.Complete the workflow by approving the workflow task item.
METALO~1_img18

Confirmation

1.Check the progress of replication on the Monitor Replicator page under the Packages tab and wait for the replication of the above actions to complete.
METALO~1_img19

2.In a web browser, open your target web application.

3.Check that the Approval workflow created above is available on both the source and target list or library.

4.Check to see that the approval workflow has run on the item on the target and the workflow status for the item is "Approved".
METALO~1_img20

In this Scenario you:

§Checked to see that the workflow task on the target was replicated and completed.

§Checked that the workflow was successfully added, and the addition was replicated from source web application to target web application.

§Checked that the workflow was successfully started, and replicated from source web application to target web application.

§Checked that the workflow was successfully completed by approving; approval was replicated from source web application to target web application.

The expected result is that Replicator is able to replicate the starting of the approval workflow and is able to replicate the approval of the item.

Setting Up Multi-Farm Replication

This scenario demonstrates how to set up a multi-hop scenario where replication will occur between three different web applications. The web applications will be called Corporate, London, and Hong Kong.

1.Set up your environment as detailed in the Metalogix Replicator Installation Guide. Be sure you set up bidirectional replication between two web applications. For this scenario we'll call these two web applications London and Corporate.

2.Enable a web application; we will call this web application Hong Kong in this scenario. In order to enable the web application for replication, go to the Configure Application page found in the Metalogix Replicator section of the SharePoint Application Management page.
METALO~1_img21

3.Go to the Manage Replication Groups page, found in Application Management for your Hong Kong web application.

4.Select Add Group and title your group "Branch Offices Group" so that it matches the group that London and Corporate are a part of. Click Ok.
METALO~1_img22

5.Set up a connection connecting Hong Kong to London. Do this by selecting Manage Replication Connections in Application Management.

6.Select Add Connection and title your group descriptively Hong Kong to London. Complete the Target Web Application section using London's information and credentials. Disregard the Target Replication Passphrase for this section.
METALO~1_img23

7.Test the connection.

8.Add Branch Offices Group to the selected replication groups and Click Ok.
METALO~1_img24

9.On your London web application go to the Manage Replication Connection page, found in Application Management. Create a connection from London to Hong Kong. The Target Web Application section should use Hong Kong's information and credentials.
METALO~1_img25

10.Test the connection.

11.Add Branch Offices Group to the selected replication groups and Click Ok.
METALO~1_img24

12.Verify that the "Portal Map Family" has replicated over to Hong Kong automatically by checking in Manage Map Families, found in Application Management.  

Confirmation

1.Verify that multi-hop replication works by opening your Corporate web application in a web browser and uploading a word document.

2.Open your London and Hong Kong web applications in web browsers and check that the change you applied to the Corporate document library has replicated over to the same library on London and Hong Kong.

3.Check the Monitor Replicator page under the Packages tab for each of the web applications to see that packages have been sent over.
METALO~1_img27

4.Check out the document on the Hong Kong web application and watch the checkout status replicate back to London and Corporate.

5.Check the Monitor Replicator page under the Packages tab for each of the web applications to see that packages have been sent over.

In this scenario you:

·Enabled a third web application.

·Created a connection for the third web application - both to and from.

·Created a replication group.

·Monitored the automatic replication of a map family.

·Added and monitored the replication of a package between all three web applications.

 

The result of this test should be that you are able to replicate changes from Corporate to London to Hong Kong and back from Hong Kong to London and Corporate.

相关文档

The document was helpful.

选择评级

I easily found the information I needed.

选择评级