Re-running Phase 2 duplication from NVBU 10 Web UI runs the original Phase 1 backup instead.
설명
When attempting to run only the phase 2 (duplication or datacopy) part of a job, from NVBU Web UI > Job History > select failed Phase 2 then click RUN NOW, the original phase 1 is started instead, running the entire job again.
해결 방안
STATUS
TFS# 26580 has been submitted to have the issue resolved in a future release of NVBU 10.
WORKAROUND
Use the CLI tool 'nvjobstart' to rerun just the secondary copy.