Full Backup: A Full Backup provides a backup of all selected files and folders. Full Backups take longer to complete and consume more backup media. However, restores are faster since the plug-in is only required to restore a single saveset. Full Backups serve as the base backups for subsequent Incremental and Differential Backups |
• |
Differential Backup: A Differential Backup provides a backup of files that are new or have changed since the last Full Backup. Differential Backups speed up recovery since the plug-in is only required to restore two savesets. However, these backups consume more storage space and take more time to complete than the Incremental Backups. Differential Backups duplicate the data backed up by previous backups of the same type. |
• |
Incremental Backup: An Incremental Backup provides a backup of files that are new or have changed since the last Full or Incremental Backup. Incremental Backups consume minimum storage space and are quicker to perform. However, data recovery can take more time depending on the number of savesets that the plug-in is required to restore. |
• |
Full Backups only: You can choose to perform only Full Backups if the backup size is small, backup window is not an issue, or storage media is not a constraint. In such scenarios, you can schedule Full Backups every night or every N hours depending on the frequency of updates. |
• |
Full and Incremental Backups: For quicker backups and minimum use of storage media, you can include Full and Incremental Backups in your strategy. For example, you can schedule Full Backups every Sunday and Incremental Backups every day or every N hours depending on the frequency of updates. |
• |
Full and Differential Backups: For quicker restores and reduced media usage, you can include Full and Differential Backups in your strategy. For example, you can schedule Full Backups every Sunday and Differential Backups every day or every N hours depending on the frequency of updates. |
1 |
In the Navigation pane, click Create Backup Job. |
2 |
In Job Name, specify a name for the job. |
3 |
In the Selections list, select an existing Backup Selection Set, or complete the following steps to create a set. |
a |
NOTE: To switch between the two views, select the ESX/ESXi or vCenter Server, and in the Actions list, click Toggle Inventory View. This option is only available when server node is open. |
• |
Back up all virtual machines within a container: Select the container node. Data selection is possible at all levels starting from the Datacenter node. |
• |
Back up individual virtual machines: Open the applicable container nodes (for example, Datacenter, Cluster, Resource Pool, and other nodes), and select the virtual machines that you want to back up. In the VMs and Templates view, open the folder node, and select the virtual machines that you want to back up. |
• |
Back up individual virtual disks: Open the virtual machine node, and select the disks that you want to back up. Note the following: |
e |
Click Save, and in the Create New Set dialog box, type a name for the set. Click Save to close the dialog box. |
4 |
In the Plugin Options list, select an existing Backup Options Set, or complete the following steps to create a set. |
a |
IMPORTANT: On Windows, when you create a Backup Options Set for image‑level backups, you must use the default set “Default Backup Options — VMware Plugin — Windows” as the template. If you use any other set as the template, the backup may fail. |
b |
Under Backup Type, select one of the following options. |
|
c |
Under VM disk selection options, select one of the following options. |
d |
Under Other Options, configure the following settings. |
| |||||
For parallel backups, the plug-in generates a parent process that coordinates the overall backup and individual child processes that perform the actual task of backing up the virtual machines. The maximum child processes that can be generated for a backup job is equal to the Maximum Number of Parallel Streams configured for the job. The parent and the child processes are all created on the NetVault Backup Client on which the plug-in is running.
When configuring Maximum Number of Parallel Streams, consider the following:
|
e |
5 |
Select or create the Schedule Set, Target Set, and Advanced Options Set. For more information about these sets, see the Dell NetVault Backup Administrator’s Guide. |
6 |
To submit the job for scheduling, click Save & Submit. You can monitor the job progress from the Job Status page and view the logs from the View Logs page. |