Scheduling repository synchronization

When using scheduled repository synchronization, savepoints are replicated to the replication repository according to a configured schedule.

1
From the Tools menu on the vRanger toolbar, select Options.
2
Under the Repositories node, select Replication.
3
In the Repository Replication Configuration pane, find the Repository Name column, and select the applicable repository.
4
Select Schedule repository synchronization.
a
Start: In the drop-down list, select the time for the replication task to begin.
b
Recurrence Pattern: Establish how often the changes should be synchronized. There are five options within this section:
Daily: The daily option can be scheduled to synchronize the repository every weekday or every x number of days.
Weekly: Repository synchronization can be configured to run on weekly intervals, from every week to every 99 weeks. The day of the week on which to run synchronization tasks can be configured.
Monthly: The monthly option offers the following configurations:
Day [x] of every [y] month:
x can be any value from 1 to 31. This value determines the day of the month on which the synchronization job occurs.
y can be any value from 1 to 99. This value determines the monthly interval — for example, every two months sets the job to run every other month.
The [f] [d] of every [y] month(s):
f can be either: first, second, third, fourth or last.
d can be: weekday, weekend day, Sunday, Monday, Tuesday, Wednesday, Thursday, Friday, or Saturday.
y can be any value from 1 to 99. This value determines the monthly interval — for example, every two months sets the synchronization task to run every other month.
Yearly: The yearly option offers the following configurations:
Every [m] [x]:
m is any month of the year. This value determines the month of the year in which the synchronization occurs.
x can be any value from 1 to 31. This value determines the day of the month on which the synchronization occurs.
The [f] [d] of [m]:
f can be either: first, second, third, fourth, or last.
d can be: day, weekday, weekend day, Sunday, Monday, Tuesday, Wednesday, Thursday, Friday, or Saturday.
m is any month of the year. This value determines the month of the year in which the synchronization occurs.
Interval: The interval option lets you select the number of days, hours, and minutes that should pass between synchronization jobs. The interval selected must be greater than or equal to five minutes.
6
Click OK to schedule the job.

Synchronizing a repository manually

1
In the My Repositories pane, right-click the source or replication repository, and select Synchronize.

Disabling repository replication

From the Tools menu on the vRanger toolbar, select Options. Under the Repositories node, select Replication.
2
Clear the check box for Enable savepoint replication for a successful backup job task or Schedule repository synchronization, or both.
3

Changing a replication repository to a primary repository

If your primary repository becomes corrupt or otherwise unavailable, you can quickly change your replication repository to a primary repository to continue backup and recovery operations.

1
In the My Repositories pane, right-click the replication repository, and click Remove.
IMPORTANT: Ensure that Delete all savepoints in this repository is not selected.
2
3
In the My Repositories pane, click Add.
5
Complete the Add Repository dialog box, and click OK.
6
When vRanger detects that the repository being added contains savepoint data and displays the Warning: Existing Repository Found dialog box, click Import to reconfigure the repository as a primary repository.
Documents connexes

The document was helpful.

Sélectionner une évaluation

I easily found the information I needed.

Sélectionner une évaluation