The Schedule option of Reports Manager was used to schedule a report. The report output was set to Email. Running the scheduled report through the Task Scheduler or through the command line results in "Unknown Error (1110)".
1. In the Reports Manger, select a report, and select the Green Arrow icon, which is "Run the Select Reports" option. This icon is on the toolbar of the Reports Manager.
2. Select the forth icon, from the Report Preview window, which is the Export icon and select E-Mail option.
3. In the Message tab, enter the e-mail address under Address field and Subject field. In the Account tab, enter the From Address, enter your Host name under Connection | Host and port which is defaulted to 25. Hit OK to send a test e-mail of the report.
4. If email was sent successfully, then try to create a new scheduled task and run it.
© 2025 Quest Software Inc. ALL RIGHTS RESERVED. Terms of Use Privacy Cookie Preference Center