This topic introduces the schedule command usage:
|
NOTE: If you specify a command without supplying the expected value or option, you will be prompted to provide the correct value or option. |
Displays any existing Cleaner schedule.
schedule --show --cleaner
Cleaner Schedule: Start Stop Sunday 05:00 06:00 Monday 05:00 06:00 Tuesday 05:00 06:00 Wednesday 05:00 06:00 Thursday 05:00 06:00 Friday 05:00 06:00 Saturday 05:00 06:00
Displays any existing replication schedule for a QoreStor. If you do not specify a name parameter, the replication schedules for all containers are returned.
schedule --show --replication --name acme55-cont1
Replication Schedule: Start Stop Sunday 22:00 05:00 Monday 22:00 05:00 Tuesday 22:00 05:00 Wednesday 22:00 05:00 Thursday 22:00 05:00 Friday 22:00 05:00 Saturday 22:00 05:00
Creates a new Cleaner or Replication schedule for a QoreStor instance.
|
NOTE: Without any Cleaner schedule set, the QoreStor Cleaner process automatically starts within two minutes after it detects that no data ingest operation or other system operation activity is present. So, if your QoreStor runs intermittent or inconsistent ingest or readback, or replication operations, there is no need to set a Cleaner schedule (it will automatically run during periods of low or non-activity). However, if your system runs regular and consistent ingest or readback you should create a Cleaner schedule that runs only during a known period of low or non-activity (for example, on a day or time period sufficient to complete this process). If your system does not meet either of these cases, you can still manually run the Cleaner. For more information, see maintenance --filesystem [--reclaim_space]. |
schedule --add --day Sunday --start_time 06:00 --stop_time 22:00 --cleaner
|
NOTE: Set a corresponding stop time for every start time in each Cleaner (or Replication) schedule you create. The following example shows setting up a Cleaner schedule for the remainder of the week (Monday through Saturday). |
|
NOTE: Do not select 00:00 for a start time or stop time endpoint for midnight when setting Cleaner or Replication schedules (instead, use either the 23:55 or 00:05 value). |
Successfully updated Cleaner schedule.
|
NOTE: To create a Replication schedule (use the QoreStor CLI --replication command), and the same process shown here to schedule the start and stop times for a Replication schedule. This lets you schedule start and stop times for each day in the week in which you want the Replication process to run. |
© ALL RIGHTS RESERVED. Conditions d’utilisation Confidentialité Cookie Preference Center