There are multiple scenarios where an ability to re-copy changes (from the source environment to the target) rather than re-copying all the content is preferable and necessary.
For example:
During a large migrations users may need to continue to make changes to the source content, or
A specific site, list or content may need to be periodically synchronized with another environment due to compliance or other business needs.
Change manager supports these scenarios using the Run Incremental feature.
STEP 1. Select an activity/group from the Activity View.
STEP 2. Select Run Incremental from the Ribbon or Action àRun Incrementa from the right-click menu.
STEP 3. The Run Activity History screen will be generated. Enter a comment into the provided interface and press the Run Now button to initiate the activity.
This action is only available for activities that copy items, list or sites.